Eskom’s improved performance shouldn’t come as a surprise

Matshela Koko. Picture: Supplied

Matshela Koko. Picture: Supplied

Published May 25, 2016

Share

Eskom has been releasing system status updates in an effort to provide transparency on its electricity generation challenges and achievements, writes Matshela Koko.

Over the last few weeks and months, Eskom has been releasing regular system status updates in an effort to provide transparency on our electricity generation challenges and achievements. These reports have highlighted our improved fleet system performance. Therefore, it should not have been a surprise, but rather a celebration, that South Africa has not had load shedding for more than nine months. Eskom does not anticipate the implementation of load shedding this winter and beyond.

Read: Winter is coming, but Eskom feels confident

Moody’s Investors Service indicated that improved electricity reliability played a key part in their recent ratings decision. A number of so-called experts have, however, raised questions as to whether this improved performance was really due to Eskom or other “factors”. Some experts have argued incorrectly that it was not due to improved Eskom performance but a reduction in demand that stopped load shedding.

Peak weekly demand

It is a fact that the energy sent out year-to-date is approximately 3 percent lower when compared with the same period last year. However, it is also a fact that the peak weekly electricity demand in week 14 was higher than last year’s peak weekly demand and Eskom was able to meet this demand comfortably. The highest peak demand (year to date) was reached on May 16 (at 6.17pm) when the system required 34 051 megawatts (MW).

Again, Eskom managed to meet this demand, and this was done without dispatching open cycle gas turbines. Another notable point is that during the peak hour, the energy output from the renewable independent power producers (IPPs) was negligible. Eskom’s capacity available at that time was 36 517MW (excluding the Ingula units) and this was also the highest capacity attained over the last three years. This capacity was attained while undertaking all planned maintenance.

The 3 percent reduction in electricity demand is therefore part, but not the whole story, of why there is no load shedding. The real story is the improved operational performance of Eskom; thanks to the leadership of Minister Lynne Brown, the stewardship of the Eskom board and the disciplined execution from the Eskom guardians.

In November 2014, the government set up the War Room. During that period, the unplanned breakdowns exceeded 8 000MW and the diesel consumption was more than 430 gigawatt-hour (GWh) at a cost of R1.4 billion per month.

Eskom needed 5 000MW in additional capacity to clear the maintenance bottleneck and to keep the lights on. Of this, 2 000MW was to come from running the open cycle gas turbines and the remaining 3 000MW was intended to come primarily from IPPs as the commercial operation dates of Medupi and Kusile power plants were delayed.

Unfortunately not all the required capacity was available, and this resulted in South Africa experiencing 318 hours of load shedding amounting to 1 062GWh (including load curtailment) during the 2015/16 financial year. The estimated cost of unserved energy is R74 a kilowatt-hour.

Eskom was determined to straighten itself up and instituted a set of stretch targets. The company had to become even more performance-focused and pedantic on the attainment of targets. A new “no excuse” culture was enforced while all required resources were provided to attain targets.

Focus on core business

This has enabled Eskom to operate within its maintenance budget of 11 500MW in summer and 8 500MW in winter. The group chief executive focused on engaging employees and instilling passion and pride in Eskom. The executive team was tasked to focus on the core business and was protected from external political influences by the Eskom board.

The results started showing from October on a number of key performance indicators. Plant availability increased from 70 percent (October) to 76 percent (April) due to better and more planned maintenance.

The increase in availability is attributable to the decrease in breakdowns (unplanned maintenance) based on the ability to undertake effective maintenance and thereby improve fleet performance. Capacity has increased by 2 599MW (excluding Medupi) and 3 279MW (including Medupi).

Importantly, all the required maintenance took place while there was a reduction in the usage of expensive open cycle gas turbines. Diesel spend was reduced from R854 million (381GWh) in October to R25m (6GWh) in April.

Additional targets of 80 percent plant availability, 10 percent planned maintenance and 10 percent unplanned maintenance over the medium term were agreed on and implemented.

Overall, this has seen current month to date performance reach 78 percent plant availability, 12 percent planned maintenance and 10 percent unplanned outages. This demonstrates steady progression towards the 80:10:10 target. This is clear evidence that the change in approach and the pedantic focus on targets is working.

As a result of the improved fleet performance, Eskom has excess capacity of up to 11 000MW between 2am and 6pm in winter. Eskom is exploring all avenues to export this excess capacity.

By stepping up and stopping load shedding, Eskom has depoliticised the provision of electricity supply as some “experts” have begun to postulate that load shedding will be a sufficient reason for a regime change. It is expected that all role players will work together, acknowledge the progress that has been made and use this as a good news story to demonstrate that South Africa is capable.

* Matshela Koko is Eskom’s group executive for generation.

** The views expressed here do not necessarily reflect those of Independent Media.

BUSINESS REPORT

Related Topics: