Eskom’s outages jump to 5‚572MW

Comment on this story
PowerLines Reuters.

Unplanned outages rose to 5‚572 Megawatts (MW) on January 7 from 4‚189MW on January 3‚ Eskom said on Monday in its 104th system status bulletin.

Eskom’s internal benchmark is to have no more than 3‚600MW in unplanned maintenance‚ a benchmark it missed more than 60% of the time last year. The last time it achieved this benchmark prior to November 29 was on August 14.

Peak demand was expected to jump from 24‚819MW on December 26 to 30‚000MW on January 9 as factories restart operations after the Christmas break. - I-Net Bridge

sign up

Comment Guidelines

  1. Please read our comment guidelines.
  2. Login and register, if you haven’ t already.
  3. Write your comment in the block below and click (Post As)
  4. Has a comment offended you? Hover your mouse over the comment and wait until a small triangle appears on the right-hand side. Click triangle () and select "Flag as inappropriate". Our moderators will take action if need be.

  5. Verified email addresses: All users on Independent Media news sites are now required to have a verified email address before being allowed to comment on articles. You are only required to verify your email address once to have full access to commenting on articles. For more information please read our comment guidelines